The Alabama Department of Transportation (ALDOT) is making final improvements on an eight-mile resurfacing project on I-20 in Talladega County.
The work to provide a fresh driving surface from the Eastaboga interchange (Exit 173) to the H.J. Bentley Jr. Parkway Overpass started in May.
Nearly 46,000 vehicles travel the six-lane section of I-20 on a daily basis.

The $6.43 million project was awarded to Vulcan Materials Asphalt and Construction after they submitted the lowest bid in September 2025.
After a few months of milling and paving at night, the final layer of asphalt is in place.

This week, contractors were out putting down permanent striping on the exit ramps and installing guardrails.

The work could be wrapped up by the end of the year.