ALDOT is expanding capacity on I-85 in Montgomery between Taylor Road and Jenkins Creek and replacing four bridges over Chantilly Parkway and the Kershaw Railroad. These improvements will improve safety, traffic flow and long-term mobility.
Visit the I-85 Chantilly project website
Get comprehensive project details including current traffic impacts, live cameras, and construction information.
| Region/County | Southeast/Montgomery |
| Type of Work | Capacity increase, bridge replacement |
| Route | I-85 from the end of the six lane to Jenkins Creek |
| Projected Start | Fall 2026 |
| Projected Completion | Summer 2030 |
| Traffic Impact | Lane closures, traffic shifts, temporary road closures |
| Project Number | NHF-IMF-I085(378) |
| Project Cost | $70,721,772.63 |
| Project Status | Active |