ALDOT to resurface SR-124 in Walker County

Resurfacing map of SR-124 in Walker County

The Alabama Department of Transportation (ALDOT) plans to resurface and install guardrail on SR-124 from the intersection of SR-118 to the intersection of SR-69 southwest of Jasper to improve mobility and safety.

The 10.8-mile project is expected to begin Thursday, July 9 and will continue until fall, weather permitting. A pilot car will guide traffic through the work zone.

Drivers should expect possible delays and are encouraged to observe work-zone speed limits.

Wiregrass Construction Company was awarded the project at $3.34 million.

For real-time traffic updates and more, download the ALGOTraffic app or visit ALGOTraffic.com.

Region/County West Central/Walker
Type of WorkResurfacing
RouteSR-124
Projected StartJuly 9, 2026
Projected CompletionFall 2026
Project NumberSTPAA-HSIP-FMGR-0124(503)
Project Cost$3,348,271.00
Project StatusActive