| Region/County | East Central/Jefferson |
| Type of Work | For constructing the Base, Pave, and Bridges on the Birmingham Northern Beltline from the junction of SR-79 to the junction of SR-75 (Partial), excluding Ramp C north of Pinson. Length 1.878 mi |
| Route | New road construction between SR-75 and SR-79 |
| Projected Start | Summer 2024 |
| Projected Completion | Fall 2026 |
| Project Number | APDF-1602(542) |
| Project Cost | $64,777,596.65 |
| Funding Source | Appalachian Development Highway System (ADHS) |
| Project Status | Active |
Birmingham Northern Beltline first phase construction between SR-75 and SR-79
It was standing room only at the Gardendale Civic Center on August 27 as the Alabama Department of Transportation (ALDOT) hosted a public forum and design hearing to gather community input on the next phase of the Birmingham Northern Beltline.
An estimated crowd over 600 residents, first responders, business leaders and area officials attended the…
Read More “Big crowd attends public forum on Birmingham Northern Beltline”
Starting this week, some property owners along the US-31 to SR-79 section of the Birmingham Northern Beltline near Pinson, Ala. will receive visits from Alabama Department of Transportation (ALDOT) representatives.
These representatives are preparing to survey properties to ensure proper roadway alignment and to evaluate environmental impacts. Engaging with property owners is part of ALDOT’s…
Read More “ALDOT reaching out to property owners along Northern Beltline route”
Engineers and other representatives from the Alabama Department of Transportation (ALDOT) will be meeting with property owners along the route of the Northern Beltline connecting US-31 to SR-79.
The representatives will survey properties to ensure proper roadway alignment and to evaluate environmental impacts. Engaging with property owners is part of ALDOT’s standard process for progressing…
Read More “ALDOT notifies public that engineers working along Northern Beltline route”
The contractor for the Alabama Department of Transportation has begun work to complete the first section of the Birmingham Northern Beltline. This initial phase of construction will be a four-lane highway connecting State Route 79 and State Route 75 in Jefferson County.
In May, the bid to construct this project was awarded to the lowest…
Read More “Work underway to open first phase of Birmingham Northern Beltline”