ALDOT to resurface portion of Greensboro Avenue in Tuscaloosa

Greensboro Resurfacing Map in Tuscaloosa

The Alabama Department of Transportation (ALDOT) plans to resurface a portion of Greensboro Avenue (SR-215) from the intersection of Skyland Boulevard (US-11) to 10th Avenue in Tuscaloosa to improve mobility and safety.

The 1.3-mile nighttime project is expected to begin Sunday, Aug. 30, and will continue for approximately two months, weather permitting.

The project will use a mill-and-fill process, with the contractor removing the existing pavement and replacing it with new asphalt. Any pavement removed overnight must be replaced before lanes reopen to daytime traffic.

Lane closures will not be allowed from 6 a.m. until 7 p.m. to reduce the impact on traffic. Additionally, lane closures will not be allowed on Saturdays when the University of Alabama has a home football game.

Drivers should expect possible delays during nighttime work and are encouraged to use caution in the work zone.

APAC-Alabama was awarded the project at $1.08 million.

For real-time traffic updates and more, download the ALGOTraffic app or visit ALGOTraffic.com.

Region/County West Central/Tuscaloosa
Type of WorkResurfacing
RouteSR-215
Projected StartAugust 30, 2026
Projected CompletionLate fall 2026
Project NumberSTPAA-FMGR-HSIP-0215(508)
Project Cost$1,081,094.00
Project StatusActive
Get the latest traffic information at algotraffic.com or on the ALGO Traffic app.