ALDOT will replace the westbound span of the bridge over the Tensaw-Spanish River, near Battleship Park.
| Region/County | Southwest/Mobile |
| Type of Work | Bridge Replacement |
| Route | US 90 Causeway in Mobile County |
| Projected Start | Winter 2025 |
| Projected Completion | Timeline: Weather permitting construction is expected to take 500 days to complete once it starts. |
| Traffic Impact | There will be some disruptions to traffic on the Causeway during the construction due to lane closures outside of peak travel times. |
| Project Number | BR-0016(522) |
| Project Cost | $78,867,874.96 |
| Funding Source | State and Federal |
| Project Status | Active |