| Region/County | East Central/St. Clair |
| Type of Work | For constructing the Safety Widening, Micro-Milling, Resurfacing (Scrub Seal), and Traffic Stripe on SR-25 (US-231) from the junction of the US-231/US-431 Roundabout to the junction of SR-23 (US-231/6th Avenue) in Ashville. Length 3.946 mi. |
| Route | US-231 (SR-25) |
| Projected Start | July 2026 |
| Projected Completion | Fall 2026 |
| Project Number | STPAA-HSIP-0025(572) |
| Project Cost | $1,775,905 |
| Project Status | Substantially Complete |
Resurfacing nearly four miles of US-231 (SR-25) in Ashville
Get the latest traffic information at algotraffic.com or on the ALGO Traffic app.
Related Posts
ALDOT is wrapping up a four-mile resurfacing project on the south end of Ashville in St Clair County.
The Alabama Department of Transportation is putting the finishing touches on a US-231 resurfacing project in the heart of Ashville.
The 3.9-mile job begins at the US-411 roundabout on the city’s southern tip and stretches north to SR-23 (6th Avenue).
The $1.77 million paving project kicked off on July 23 after ALDOT awarded Wiregrass…
Read More “US-231 resurfacing project in Ashville near completion, courthouse square work continues”