Mitchell Boulevard northbound bridge deck poured

Workers direct a boom pouring concrete on a bridge
Miller & Miller poured concrete for the northbound US-43/US-72/Mitchell Boulevard bridge deck early Tuesday.
Jul 29, 2026

The $7.2 million replacement of the US-43/US-72/Mitchell Boulevard bridge over SR-20 in Florence reached a milestone this week when contractor Miller & Miller poured concrete for the northbound bridge deck early Tuesday.

Miller & Miller poured about 150 cubic yards of concrete, transferred onto the bridge via a boom pump. Workers leveled the concrete as it was poured, then finished the surface that will carry traffic in the future.

A worker on a gantry silhouetted by the morning sun above a freshly-poured concrete bridge deck
About 150 cubic yards of concrete, transported to the site aboard 17 mixer trucks, went into the bridge deck.

Tags

Related Project
A map of the planned bridge replacement.
Region/County North/Lauderdale
Type of WorkBridge Replacement
RouteUS-43/US-72
Projected StartMarch 2026
Projected CompletionSpring 2028
Traffic ImpactSouthbound/westbound roadway reduced to one lane; detour for northbound/eastbound traffic

This project will replace the bridge on US-43/US-72 over SR-20 constructed in 1938 with a clear span bridge, improving clearance and safety.

Read More “Mitchell Boulevard bridge replacement”