Part of I-59N opened to traffic after reconstruction

An exit sign for Sulphur Springs next to a new asphalt roadway
The opening of the recently-reconstructed segment of the northbound I-59 roadway included reopening the northbound ramps of Exit 239 at County Road 140.
Nov 06

A four-mile segment of the reconstructed northbound I-59 roadway near the Georgia state line opened to traffic today. The opening marks the halfway point for a $41 million project to reconstruct part of I-59 in DeKalb County.

The roadway opening between mileposts 237 and 241 included reopening the northbound on- and off-ramps of Exit 239 at CR-140/Sulphur Springs Road.

Please expect single-lane closures in the work zone for removal of temporary crossovers. Visit ALGOtraffic.com or download the ALGO Traffic app for real-time traffic and road condition information and to subscribe to personalized traveler alerts.

Second phase to come

The contractor, Wiregrass Construction, will next prepare to remove and replace another four miles of the northbound roadway. The second phase of the project will run from about milepost 233, north of Hammondville, to about milepost 237, immediately south of the recently reconstructed segment.

The northbound roadway will close for demolition and reconstruction. Northbound traffic will be diverted to the inside lane of the southbound roadway and separated from southbound traffic by barriers.

The total project will reconstruct more than eight miles of the northbound roadway between Hammondville and the state line. ALDOT anticipates completion in late 2026.

I-59 reconstruction projects

Age and deterioration of the underlying concrete roadways led ALDOT undertake reconstructing much of I-59 in DeKalb and Etowah counties. The effort is ongoing, with future projects planned in addition to two current projects. ALDOT has awarded nearly $192 million in contracts to reconstruct I-59 so far.

Contractor Vulcan Materials is working to reconstruct nearly eleven miles of the southbound roadway in Dekalb and Etowah counties. ALDOT anticipates 2027 completion of that segment, between Collinsville and Reece City, at a cost of $40.7 million.

ALDOT previously completed three reconstruction projects on the corridor:

  • In 2022, Wiregrass finished replacing eight miles of the northbound roadway through Fort Payne at a cost of $25.2 million.
  • The following year, Wiregrass completed reconstruction of eleven miles northbound between Reece City and Collinsville at cost of $44 million.
  • Earlier this year, contractor A.G. Peltz Group completed replacement of an eight-mile segment between Fort Payne and Hammondville at a cost of $40.8 million.
Related Project
Two roadways viewed from above. On the left is the southbound roadway with concrete barrier running down the middle.
Region/County North/Dekalb
Type of WorkReconstruction/Asphalt pavement
RouteI-59
Projected StartMay 2024
Projected CompletionFall 2026
Traffic ImpactSingle-lane closures northbound and southbound and shift of all traffic to southbound roadway, separated by concrete barrier.

This project will reconstruct (pavement removal, grading, drainage, pavement and traffic stripe) more than eight miles of the I-59 northbound roadway from north of SR-40/SR-117 in Hammondville to the Georgia state line.

Read More “I-59 Northbound Reconstruction from Hammondville to Georgia line”