| Region/County | East Central/Jefferson |
| Type of Work | For constructing the micro-milling, resurfacing, guardrail installation, and traffic stripe on I-20/I-59 from a point south of the Fairfield Boulevard Bridge (MP 116.290) to a point south of the Valley Road Bridge (MP 118.277) in Fairfield. Length 1.985 mi |
| Route | I-59/20 |
| Projected Start | February 2026 |
| Projected Completion | Summer 2026 |
| Project Number | IM-IMGR-I059(459) |
| Project Cost | $1,503,935.95 |
| Project Status | Active |
I-59/20 resurfacing between Fairfield Boulevard and Valley Road Bridges