Safety widening, resurfacing, guardrail installation and traffic striping on US-31 from the junction of Inverness Drive in Clanton to the junction of Collins Street in Thorsby. Additionally, US-31 will be restriped from the existing four lanes to three lanes from just north of Cherokee Road to Medical Center Drive.
| Region/County | West Central/Chilton |
| Type of Work | resurfacing, guardrail installation, traffic striping, widening |
| Route | US-31 |
| Projected Start | February 26 |
| Projected Completion | Summer 2024 |
| Traffic Impact | Motorists should expect possible delays and are encouraged to observe work-zone speed limits. Lane closures are only allowed between 7 p.m. and 6 a.m. to reduce the impact to traffic. |
| Project Number | STPAA-HSIP-0003(646) |
| Project Cost | $4,524,853.00 |
| Project Status | Completed |


